Valley Rail

What is Valley Rail?

Valley Rail is a joint program that includes improvements and expansions of both ACE and Amtrak San Joaquins that is focused on improvements between Sacramento and the San Joaquin Valley. Valley Rail implements two new daily round-trips for the Amtrak San Joaquins service to better connect San Joaquin Valley travelers with the Sacramento Area, and extends Altamont Corridor Express (ACE) service between Sacramento and Merced. In addition, Valley Rail will convert the entire fleet including the thruway bus network to renewable diesel fuel, providing greenhouse gas (GHG) benefits across the entire existing (449 track miles) and proposed expanded (119 track miles) San Joaquins and ACE services.

Valley Rail's Latest

Federal Infrastructure Bill Brings Major Investment to California Rail Network

For Immediate Release Federal Infrastructure Bill Brings Major Investment to California Rail Network Funding Package Supports Several ACE Rail and …

Federal Infrastructure Bill Brings Major Investment to California Rail Network Read More »

  Read More Federal Infrastructure Bill Brings Major Investment to California Rail Network

EIR Released for Valley Rail Project

PRESS RELEASE FOR IMMEDIATE RELEASE December 3, 2020 Stockton Diamond Grade Separation Project Wins $100 Million TCEP Grant from State …

EIR Released for Valley Rail Project Read More »

  Read More EIR Released for Valley Rail Project

EIR Released for Valley Rail Project

EIR Released for Valley Rail Project Public Comment Period Now Open Regarding Track Improvements, New Station Buildout, and Increased Passenger …

EIR Released for Valley Rail Project Read More »

  Read More EIR Released for Valley Rail Project

Station Project Updates

The Valley Rail Projects that aim to improve travel in the San Joaquin Valley, Sacramento, and the Bay are in various project phases. The dropdown menu allows you to view current project phases: Planning, Design, Construction, and Completed.

Key

  • San Joaquins Rail
  • ACE Rail
  • ACE Rail, San Joaquins Rail

Project Highlights

vr-icon-1
New stations

16 new stations are being constructed

vr-icon-2
Increased Service

7 new daily round-trips will be added between the two services

IMG_4609
Serving the community

30% of disadantaged communities in California served

vr-icon-4
Environmental Benefits

52 Million metric tons of C02 GHG

Rectangle-5-1 (1)
Community Health

Improve public health and reduce Fataties/Injuries

vr-icon-7
New Equipment

New trainsets for ACE and San Joaquins

Why is Valley Rail Important to California?

Valley Rail improves geographic equity by connecting key locations in the Central Valley including Sacramento, San Joaquin, Stanislaus, Merced, Madera, and Fresno Counties to each other and beyond to the Bay Area and the greater California rail network via three future high-speed rail (HSR) connections in Merced and San Jose. This transformative, megaregional project helps further the State's vision for an integrated rail network and provides direct mobility and air quality benefits to citizens in nine counties, including over 30% of the disadvantaged communities in California.  SJJPA SJRRC TIRCP Grant Announcement Press Release

Based on environmental clearance and funding, the Valley Rail Program consists of two segments one South and one North of Stockton. Each segment includes several projects each with individual costs and schedules.

Current contract work includes engineering and property assessments for different station and track work locations at Ceres, Modesto, Manteca, Lathrop, Stockton, Lodi, Elk Grove, Midtown Sacramento, and Natomas. Additional contracts will be awarded in the future for stations and associated track work.

ACE-Maintenace-Facility (1) 1

Milestones

2016

Secured $16.4 million in TIRCP funding from the state to expand ACE platforms to accommodate longer trains

April 2017

Secured $400 million in state funding from SB 132 for ACE to extend to Ceres

July 2017

In preparation for the 2018 TIRCP application, a joint SJRRC/SJJPA study called for investment in five new stations in Sacramento region and connectivity to the HSR network for intercity service between Sacramento and the Central Valley, consistent with HSR Connected Corridors Study


April 2018

Secured $500.5 million in TIRCP funding from the state for the Sacramento Extension


August 2018

Completed the Final EIR for Modesto/Ceres Segment


September 2018

Caltrans released the California State Rail Plan that highlighted the vision for expanded San Joaquins and ACE service including additional trains and new stations and the extension north of Sacramento

October 2019

SJRRC created the Station/Facilities Development Committee to make decisions and reflect community interests in the design and delivery of new stations for Valley Rail

2019

Affordable Housing Sustainable Communities (AHSC) Partnerships with SJRRC:

Secured $17.9 million for Grand View Village, Visionary Home Builders, a 62-unit affordable housing project in downtown Stockton west of Cabral Station, including $9.9M for affordable housing, $4 million for ACE rail car and $3.7 million for other transportation projects and programs

Secured $24.7 million for Archway Commons, EAH Housing in Modesto, a 73-unit affordable housing project, with a grant of $4 million for ACE rail car

February 2020

CHSRA Business Plan included direct connections with Valley Rail services in Merced

September 2020

Awarded $20 million in federal funding from the Better Utilizing Investments to Leverage Development (BUILD) Transportation Discretionary Grants program for the Stockton Diamond project

October 2020

Completed Final EIR for Sac Extension

November 2020

SJJPA signed an MOU with CHSRA and CalSTA to position SJJPA to be the rail service provider of the Interim HSR Service

December 2020

Awarded $100 million in Trade Corridor Enhancement Program (TCEP) funding through California's SB 1 to support the Stockton Diamond project

January 2021

SJRRC signed MOU with the Tri-Valley - San Joaquin Valley Regional Rail Authority to position SJRRC to operate future Valley Link commuter rail service to connect BART's rapid transit system to the ACE commuter service


August 2021

SJRRC Station/Facilities Development Committee approved 'Design Principles' for Valley Rail stations - 1) People-First Approach, 2) Serving All Communities, 3) Design Continuity, 4) Durable and Resilient, 5) Adaptable for the Future

Summer 2021

Butte County Association of Governments (BCAG) was awarded $500,000 in Caltrans Sustainable Transportation Planning Grant Funds to examine North Valley Extension in partnership with SJRRC and SJJPA


November 2021

SJRRC Station/Facilities Development Committee approved the Valley Rail Station Design Guidelines on areas including site circulation, landscape, vertical circulation, platform, wayfinding, facilities, infrastructure

Metropolitan Transportation Commission (MTC) released Phase 1 of the SoCo Rail Study to look at creation of an East Bay rail-to-rail transfer hub in Southern Alameda County to serve as the nexus for megaregional rail services and Bay Area rail and bus services

December 2021

Completed Final EIR for Ceres to Merced

Completed Final EIR for Stockton Diamond

Completed Stockton Diamond NEPA

Competed Final EIR for Elk Grove Station

2021

Affordable Housing Sustainable Communities (AHSC) Partnerships with SJRRC:

Secured $27 million AHSC grant award with Service First of California for the Hunter House Project, a 120-unit affordable multifamily housing project for special needs populations, with grant including $9.4 million for transportation improvements that includes street improvements, $2.5 million for a new ACE railcar, and $1.35 million for improvements to Cabral and San Joaquins Street stations

Secured $29 million AHSC grant award with EAH Housing for the On Broadway Project (140-unit affordable multifamily housing), with $10 million for transportation improvements that includes street improvements, $6.1 million for two new ACE railcars, and $1.3 million for improvements to Midtown Station

January 2022

BCAG began work on a strategic plan for the North Valley Rail Extension from Sacramento to Chico

March 2022

Federal FY 2022 omnibus spending package included $4.4 million for the Manteca station project, $1.5 million for the North Lathrop Transfer station project, and $1.5 million for an ACE battery-powered locomotive pilot program

May 2022

SJRRC announced The Rail Academy of Central California (TRACC) in partnership with Sacramento City College and Stockton Unified School District to train and place students into quality transportation-related jobs in railroad and transit sectors

July 2022

Received $57 million in TIRCP funding from the state for Ceres-Turlock

October 2022

Began environmental review for Merced Intermodal Track Connector (MITC)

November 2022

SJRRC Station/Facilities Development Committee approved the Station Design Criteria to provide specific direction and standards

November 2022

ACE became the first Northern California commuter rail service to switch to 100% renewable diesel operations as part of its Climate Action Plan, reducing GHG emissions by 99%

January 2023

Federal FY 2023 omnibus spending package included $1.5 million to support workforce development activities at the Stockton Rail Maintenance Facility and $2.1 million for a state-of-good-repair project at the San Joaquins station

February 2023

Awarded $142 million in TIRCP funding from the state to support station construction in Natomas, Elk Grove, North Lathrop, Manteca, Modesto, Ceres, and Madera, ACE platform extensions at Lathrop/Manteca, Tracy, Vasco Rd, Livermore, and Pleasanton stations, and the Stockton Diamond Grade Separation project


June 2023

Awarded (application for $40 million) from the state's Trade Corridor Enhancement Program (TCEP) to Caltrans and SJRRC for Ceres to Turlock Double Track Project. Completion of the Southern Alameda County Integrated Rail Analysis (SoCo Rail) Study. MTC Link and SJRRC Link.

Anticipated Future Milestones

Fall 2023

Final plan completed for North Valley Rail

2024

Construction begins on Valley Rail track and stations

2025

Construction of Madera Station and Oakley Station Complete.

End of 2026

New stations open in Natomas, Midtown, Elk Grove, Downtown Manteca, Modesto, Ceres

One new ACE Round-Trip Ceres to San Jose

One Existing ACE Round-Trip Extended to Natomas

End of 2027

New stations open in Lodi, Ripon, North Lathrop Transfer Station

Stockton Diamond Grade Separation completed

Two new ACE Round-Trips Ceres to Natomas with ability to transfer to/from San Jose at North Lathrop Transfer Station

One new intercity Round-Trip Stockton to/from Natomas

2029

New stations open in Old North Sacramento (subject to City of Sacramento Redevelopment Study), City College, Turlock


One new San Joaquins Round-Trip Stockton to/from Natomas


Ceres - Turlock Extension


2030-2033

New stations open in Livingston, Atwater (subject to local funding) Merced (new)

Extensions open for Union City and North Valley

Service optimized to meet HSR, including includes additional (5) round-trips from Merced to Natomas (one of these replaces a round-trip between Stockton and Sacramento), the extension of four round-trips to Chico, the three round-trips to/from Union City, and the one additional round trip between Merced and Oakland.

Madera HSR Station improvements completed for the HSR EOS service.

MITC Project completed.

Valley Rail Station Design Guidelines

Valley Rail will consist of shared ACE and San Joaquins stations between Stockton and Natomas, ACE stations for the extension from Lathrop to Ceres/Merced, and San Joaquins stations at Oakley and Madera. As SJJPA/SJRRC have made passenger experience a priority, there is a strong need for blended policies to guide elements of station design and delivery. Additionally, as the program will be implemented through multiple station design projects, with different design teams and over a duration of time, the agency felt there was need for unified principles, guidelines and criteria. These will help guide station and system designs for visibility, safety, and passenger accommodation while reflecting quality design and relating to their local environment. The overall design goal is to balance consistent system-wide functional continuity, while providing distinctive elements that are reflective of surrounding neighborhood character.

The document can be found here.